Since the first galvanising plant OTN1 went into operation successfully in September 2004, the decision was made to construct a second plant in another strategic part of Austria.
The plant concept was in principle maintained, but some improvements that were identified in the first few years at OTN1 found their way into the concept.
The tried and proven project team managed to realise this plant in only 135 days of construction. The plant was started up in February 2007.
With a tank size of 15.5 x 1.8 x 3.2 m, the plant has the largest zinc bath in Austria and is designed for an annual capacity of 40,000 tons.